By Brandon Bennett |STURGIS|
Editor’s Note: I felt it better to copy the plan so there’s no confusion. I apologize for its length.
The Meade 46-1 school board heard of the Master Facility Plan for the
fiscal years 2027-2029
The Meade School District 46-1 is dedicated to maintaining facilities that support and enhance an effective
learning environment for our students. This plan provides a three-year outlook at the projects and improvements that the
Meade School District 46-1 will be preparing to implement in the Capital Outlay Budget. Please note that these numbers are
estimates and may change with time and economic variables.
Sturgis Brown High School
Fiscal Year Project Description Estimated Cost
2026-2027 West gym doors, East gym locker-room & training room, electrical system A&E 143,000
2027-2028 Roofing, Electrical system upgrade, HVAC $900,000
2028-2029 LED lighting, Roofing, windows $700,000
SBHS CTE Addition Project $25,000,000
Sturgis Williams Middle School South/Williams North
Fiscal Year Project Description Estimated Cost
2026-2027 Electrical systems upgrade $240,000
2027-2028 Roofing $235,000
2028-2029 Interior improvements $75,000
Stagebarn Middle School
Fiscal Year Project Description Estimated Cost
2026-2027 interior improvements $20,000
2027-2028 Mult-purpose room door $60,000
2028-2029 Parking lot addition $350,000
Sturgis Elementary
Fiscal Year Project Description Estimated Cost
2026-2027 Phase III roof replacement, playground improvements $419,000
2027-2028 Replace gutter, Interior improvements $100,000
2028-2029 Replace East fence, interior improvements $105,000
Whitewood Elementary
Fiscal Year Project Description Estimated Cost
2026-2027 Security fence playground $35,000
2027-2028 Playground improvements $TBD
2028-2029 HVAC, Interior improvements $TBD
Piedmont Valley Elementary
Fiscal Year Project Description Estimated Cost
2026-2027 Roof replacement $550,000
2027-2028 Playground improvements $325,000
2028-2029 HVAC, Interior improvements $105,000
Woodle Field
Fiscal Year Project Description Estimated Cost
2026-2027 Field improvements $1,300,000
2027-2028 Bleacher addition $TBD
2028-2029 TBD $TBD
Building & Grounds/ Central Copy
Fiscal Year Project Description Estimated Cost
2027-2028 Roof replacement central copy $65,000
2028-2029 Facility upgrade/vehicle storage TBD
Rural Facilities
Fiscal Year Project Description Estimated Cost
2026-2027 Exterior improvements/CMCS playground $35,000
2027-2028 Water filtration CMCS, playground improvements, interior improvements $100,000
2028-2029 TBD $TBD
School Security Improvements
Fiscal Year Project Description Estimated Cost
2026-2027 District wide improvements $125,000
2027-2028 District wide improvements $125,000
2028-2029 District wide improvements $125,000